Impact Factor (2025): 6.9
DOI Prefix: 10.47001/IRJIET
Good construction planning is one of the requirements for successful
construction. This spillway construction with contract value of
IDR99,939,304,966, - was under-schedule so that would affect the rest of the
construction costs and duration. Then this study will discuss the optimization
of rest costs and duration of this spillway construction. The solution in this
study uses trial and error with CPM (Critical Path Method) and will get optimal
costs and duration for the rest construction. The rest duration for the initial
plan for construction of spillway is 192 days (9 months) with the rest contract
cost of IDR46,593,769,076.80. Then control the time and cost of the remaining
work using crashing with the method of adding labor and overtime work. A trial
and error I result is IDR47,613,769,076.80 and IDR47,260,089,076.80 the
efficiency duration is 6 months. Furthermore, trial and error 2 resulted in
IDR47,721,769,076.80 and IDR 47,272,969,076.80 with a completion duration in 7
months, next trial and error 3 resulted IDR 46,621,669,076.80 and IDR
46,610,389,076.80 with 8.5 months. From the calculations and graphs of the
three trials and errors get the conclusion for optimum cost results are
IDR47,760,000,000,- with additional labor and IDR47,300,000,000,- with overtime
work methods and the optimum duration is 138 days.
Country : Indonesia