Effect of Bored Pile Foundation Implementation on Environment, Cost of Elevated Railway Construction Project Between Solo Balapan-Kadipiro KM 104 + 700 to KM 107 + 000 (Phase 1)

Abstract

The high volume of vehicles at Simpang Joglo, which caused traffic congestion, became a particular focus for the government. The construction of the bridge on this railway line of PT. Wijaya Karya (WIKA) is located at KM 105+499 to KM 105 +772, with a bridge stretch of 272.80 m and a width of 14.1 m. The problems raised in this study include the effect of the implementation of bored pile work on the environment, whether the solution to the problem affects cost and time, and how much the carrying capacity of the bored pile is at this stage, using qualitative research methods and quantitative research methods. After observations and interviews with the community, it can be known that the bored pile foundation work on the Railway Elevated Line Construction Project between Solo Balapan - Kadipiro at KM 104 + 700 to KM 107 + 000 (phase 1) has several impacts that affect the work environment and the community environment, including noise, road damage, air pollution, land collapse due to drilling damage to tools, etc. From this impact, there are several solutions, including repairing road facilities, changing tools, etc. From the results of the analysis of the calculation of the bearing capacity of the foundation at Pier 11, a value of 28135.397 kN was obtained. The benefits of this research are that it can find out problems and solutions for work, know the impact on time and cost, and know the carrying capacity of a bored pile.

Country : Indonesia

1 Adeline Faustina Supono2 Co. Prof. Muhammad Nur Sahid

  1. Civil Engineering, Universitas Muhammadiyah Surakarta, Indonesia
  2. Civil Engineering, Universitas Muhammadiyah Surakarta, Indonesia

IRJIET, Volume 7, Issue 3, March 2023 pp. 142-149

doi.org/10.47001/IRJIET/2023.703021

References

  1. Davidson, J (2002). Manajemen Poyek Yogyakarta : Andi.
  2. Hardiyatmo. H. C, 2015, Analisi dan  Perancangan Fondasi II, 2027.48.05.15, edisi ke tiga, Gadjah Mada University Press, Yogyakarta.
  3. Listyawan. A. B, et al, 2017, Mekanika Tanah dan Rekayasa Pondasi, ISBN: 978-602-361-058-7, Muhammadiyah University Press, Surakarta.
  4. PemerintahPusat, Peraturan Pemerintah Republik Indonesia No 50 Tahun 2012 Tentang Penerapan Sistem Manajemen Keselamatan dan Kesehatan Kerja, no. Cd. Indonesia : LN. 2012 No. 100, TLN No. 5309, LL SETNEG : 17 HLM, 2012, p. b usaha- usaha. [Online]. Available :
  5. https://peraturan.bpk.go.id/Home/Details/5263/pp-no-50-tahun-2012
  6. Sahid M. N. et al, 2020, Faktor-Faktor Penyebab Pembengkakan  Biaya oleh Kontraktor Proyek Jalan Kota Solo, Jurnal Litbang Sukowati,  Vol.4.No.1, Hal 24-36.
  7. Sahid M. N. et al, 2019,Analisis Faktor-Faktor Penting Penyebab Masalah Penambahan Biaya pada Proyek Jalan Kabupaten Klaten, Jurnal Media Teknik Sipil, Jilid 17, Hal 1-8.
  8. SahidM. N. et al, 2019, Analisis Faktor Dominan yang Mengakibatkan Pembengkakan Biaya oleh Kontraktor pada Proyek Jalan Kabupaten Wonogiri APBD Tahun 2017 dan 2018, Cantilever, Vol. 8. No.2.
  9. Sahid M. N, 2019.Kajian Faktor-faktor penyebab cost Overrun pada Proyek Konstruksi Jalan dengan APBD Kabupaten Sukoharjo Tahun 2017 dan 2018, Jurnal Teknik Sipil Universitas Syiah Kuala, Vol. 8. No. 2.
  10. Soeharto, Iman. 1999. ManajemenbProyek (Dari
  11. Konseptual Sampai Operasional) Edisi Kedua Ja-
  12. karta : Erlangga.
  13. Sosrodarsono. S, Nakazawa. K, 2000, Mekanika Tanah dan Teknik Pondasi, ISBN 979-408-174-4, Pradnya Paramita, Jakarta.
  14. Susanto. A. et al, 2020, Perencanaan Fondasi Tiang Bor Abutmen Jembatan Kali Kendeng, Dinamika Teknik Sipil, Vol.13, No.2, Hal 30-36.