Solar Power Plants are a form of
renewable energy that harness sunlight to generate electricity through solar
panels. This research designs a PLTS system for use at the Labuan Steam Power
Plant (PLTU) of PT. PLN (Persero), aimed at reducing the plant's own
electricity consumption. This study evaluates the design and installation of a
PLTS system on a 7200 m² area at the Labuan PLTU and conducts a technical and
economic comparison between On-Grid and Off-Grid PLTS systems. The research
methods include field surveys, shading potential measurements, and design
simulations using PVSyst software. The results show that the On-Grid PLTS
installation at the Labuan PLTU Administration Building is technically and
economically feasible, with a Benefit-Cost Ratio (BCR) of 1.20 and a Payback
Period (PP) of 16.93 years. The implementation of this PLTS system has the
potential to reduce carbon emissions by 84,187 tons of CO₂e per year, supporting PT. PLN's program to achieve the 23%
renewable energy mix target by 2025.
Country : Indonesia
IRJIET, Volume 8, Issue 10, October 2024 pp. 13-16