Reliability Analysis of Electric Vehicle Charging Station Using Risk-Based Inspection Method and Reliability Block Diagram

Abstract

Due to the increasing market demand for electric vehicles, particularly electric cars, the infrastructure for electric vehicles is also being fulfilled. This research utilized two methods: Risk Based Inspection and Reliability Block Diagram. Through the Risk Based Inspection method, a Risk Priority Number was obtained which identifies critical points in the Electric Vehicle Charging Station (EVCS). The Block Diagram method established relationships between interconnected subsystems. The research findings indicate that the critical point of the EVCS lies within the Body subsystem. This discovery significantly contributes to raising awareness about EVCS, ensuring that stakeholders entering the EVCS business have a clearer understanding and knowledge of the system.

Country : Indonesia

1 Falih Setiawan2 Gunawan Dwi Haryadi3 Ismoyo Haryanto4 Toni Prahasto5 Achmad Widodo6 Ojo Kurdi

  1. Mechanical Engineering Student, Faculty of Engineering, Diponegoro University, Jl. Prof. Sudharto, SH., Tembalang-Semarang 50275, Indonesia
  2. Lecturer in the Department of Mechanical Engineering, Faculty of Engineering, Diponegoro University, Jl. Prof. Sudharto, SH., Tembalang-Semarang 50275, Indonesia
  3. Lecturer in the Department of Mechanical Engineering, Faculty of Engineering, Diponegoro University, Jl. Prof. Sudharto, SH., Tembalang-Semarang 50275, Indonesia
  4. Lecturer in the Department of Mechanical Engineering, Faculty of Engineering, Diponegoro University, Jl. Prof. Sudharto, SH., Tembalang-Semarang 50275, Indonesia
  5. Lecturer in the Department of Mechanical Engineering, Faculty of Engineering, Diponegoro University, Jl. Prof. Sudharto, SH., Tembalang-Semarang 50275, Indonesia
  6. Lecturer in the Department of Mechanical Engineering, Faculty of Engineering, Diponegoro University, Jl. Prof. Sudharto, SH., Tembalang-Semarang 50275, Indonesia

IRJIET, Volume 8, Issue 9, September 2024 pp. 290-296

doi.org/10.47001/IRJIET/2024.809035

References

  1. Adigama, A. S. (2011), Penyusunan Schedule Perawatan Sepeda Motor Honda Supra X 123 Sub-Assembly Rem Berbasis Reliability Centered Maintenance (RCM) Diponegoro University.
  2. Ebeling, C. E. (1997). An Introduction to Reliability and maintainability Engineering. Dalam T. McGraw (Penyunt.). New York, USA: Hill Companies.
  3. Kumar, G., Jain, V., Gandhi, O.P., 2013. Availability Analysis of Repairable Mechanical System Using Analytical Semi-Markov Approach. Quality Engineering, 25: 97-107. https://doi.org/10.1080/08982112.751606
  4. Limantoro, D. (2013). Total Productive Maintenance di PT. X. Jurnal Tirta, 1(1), 13-20.
  5. Ludeand, D., Cretu, A., Munteano, R., Moga, R., Storia, N., Moga, D., Vladereanu, L., 2018. Reliability Approach of a Compressor System using Reliability Block Diagrams. Journal of Funadamental abd Applied Science, 10: 149-154. http://dx.doi.org/10.4314/jfas.v.v10i4s.74.
  6. Mokhtar, A.A., Muhammad, M., Hussin, H., Majid, M.A.A., 2011. Developmennt of a RAM Simulation Model for Acid Gas Removal System. International Journal of Mechanical and Mechatronics Engineering, 5: 2587-2590.
  7. O’Connor, P.D.T., and Andre, K. 2012. Practical Reliability Engineering. Priyanta. Dwi, (2010), Keandalan dan Perawatan. Institut Teknologi Sepuluh November Surabaya.
  8. Rachman, H., Garside, A.A K., & Kholik, H. M. (2017). Usulan Perawatan Sistem Boiler dengan Metode Reliability Centered Maintenance (RCM). Jurnal Teknik Industri, 18(1), 86-93.
  9. Rajput, B.S., Vaishali Choury, 2015. UML based Approach for System Reliability Assessment. International Journal off Computer Applications, 131: 17-24.
  10. Sianipar, H., 2008. Evaluasi Program Pemeliharaan Pabrik Amoniak Usulan dan Pemecahannya dalam Usaha Mengurangi Shutdown Pabrik dan Memperpanjang Turn Around Interval (Studi Kasus di Unit Front End pabrik Amoniak PT. Pupuk Kaltim). Tesis, Universitas Gajah Mada, Program Studi Teknik Mesin.
  11. Smith, D.J., 2011. Reliability, Maintainability, and Risk.
  12. Sunderam, G., Mohan, R., 2011. Integrated System Reliability Analysis for Wind Turbine. International Journal of Production Technology and Management Research. 2: 9-16.
  13. Taufik, & Septyani, S. (2015). Penentuan Interval Waktu Perawatan Komponen Kritis pada Mesin turbin di PT PLN (Persero) Sektor Pembangkit Ombilin. Jurnal Optimasi Sistem Industri, Vol. 14, No. 2, pp. 238-258.
  14. Tupan, J. M., Camerlang, B. J., & Amin, M. (2019). Penentuan Jadwal Perawatan Komponen Kritis pada Mesin MTU 12V2000G65 di PLTD Tersebar PT PLN (Persero) Area Tual. Arika, 13(1) 33-48.