Controlling Project Cost and Time with the Result Value Concept Method

Co. Prof. Muhammad Nur SahidCivil Engineering, Universitas Muhammadiyah Surakarta, IndonesiaIndra Wahyu NusantaraCivil Engineering, Universitas Muhammadiyah Surakarta, IndonesiaTsulis Iq’bal Khairul AmarCivil Engineering, Universitas Muhammadiyah Surakarta, IndonesiaAlfia MagfironaCivil Engineering, Universitas Muhammadiyah Surakarta, Indonesia

Vol 9 No 1 (2025): Volume 9, Issue 1, January 2025 | Pages: 106-112

International Research Journal of Innovations in Engineering and Technology

OPEN ACCESS | Research Article | Published Date: 20-01-2025

doi Logo doi.org/10.47001/IRJIET/2025.901013

Abstract

Construction projects play an important role in supporting infrastructure development. However, there are often deviations between the initial plan and actual implementation, either in terms of money or time, which can result in delays and cost overruns. This study aims to examine the implementation of the Earned Value Concept Method in controlling costs and time on the Trasan II Bridge Replacement Project in Klaten Regency. The study results prove that until week 15, the project has exceeded the plan target with a realization of 81.38%, higher than the plan of 35.21%. The SPI of 2.207813348 indicates a time performance that is ahead of schedule, but the CPI of 0.995142328 indicates the costs incurred exceeded the plan budget. The projected remaining cost (ETC) is Rp701,350,409.24, and the remaining completion time (ETS) is estimated at 4,759 weeks. In addition, analysis using the Precedence Diagram Method (PDM) identified a critical path involving seven activities with a total duration of 21 days. Rescheduling was carried out to optimize project implementation. This study provides recommendations to improve project management efficiency through periodic performance evaluation and integrated control using the Earned Value Concept Method.

Keywords

Control, Earned Value Concept, Optimum


Citation of this Article

Co. Prof. Muhammad Nur Sahid, Indra Wahyu Nusantara, Tsulis Iq’bal Khairul Amar, & Alfia Magfirona. (2025). Controlling Project Cost and Time with the Result Value Concept Method. International Research Journal of Innovations in Engineering and Technology - IRJIET, 9(1), 106-112. Article DOI https://doi.org/10.47001/IRJIET/2025.901013

References
  1. Dewi, Sari Utama, and I. Wayan, and Ranu Mandira. 2023. ANALYSIS OF TIME AND COST MANAGEMENT IN BUILDING CONSTRUCTION PROJECTS USING THE CONCEPT OF THE RESULT VALUE METHOD. Vol. 04.
  2. Fidina Bella, Aisyah, Co Muhammad, and Nur Sahid. 2023. “Effect of Pile Foundation Implementation on Environment, Cost of Elevated Railway Line Construction Project Between Solo Balapan-Kadipiro KM 104+700 to KM 107+000 (Phase II).” International Research Journal of Innovations in Engineering and Technology (IRJIET) 7(3):132–41. doi: 10.47001/IRJIET/2023.703020.
  3. Kejari Evidence Building in Talaud Islands Regency Joshua Goha, Pembangunan A., Tisano Tj Arsjad, and Pingkan AK Pratasis. n.d. "Earned Value Analysis on Projects."
  4. Hayati, N. I., & Lugi, D (2020). Evaluation of Cost and Time with Earned Value Management Method (Case Study: Damara Village Shophouse, Kel. Ciparagi, Bogor City). Journal of Civil Engineering and Environmental, 4 (1).
  5. Kartika, Widya, Buddewi Sukindrawati, and Nurrosyid Aldian. n.d. Cost and Time Control on the Implementation of the Borobudur Tourism Area Concourse Project with the Result Value Concept Method.
  6. Nasution, F., & Syahrizal. (2017). Application of Earned Value Concept Method in Project Control (Case Study: Jasindo Building Utility Construction and Addition Project). USU Journal of Civil Engineering, 06(01).
  7. Nono, Y., Pratasis, P. A. K., & Malingkas, G. (2019). Analysis of Value for Money Method on Time and Cost of Office and Distribution Center Project, AIRMADIDI, NORTH MINAHASA MANADO. Journal of Civil Statics, 7(11), 1465-1467.
  8. Rani, H. A. (2016). Construction Project Management (H. A. Rani (ed.)). Deep Publish. https://www.researchgate.net/publication/316081639.
  9. Sahid, Muh Nur, Agus Riyanto, Abdul Rochman, Mohd Adib Bin, Mohammad Razi, Hussein Onn Malaysia, and Adila Chilmayanti. n.d. CONTROLLING OF TIME AND COST IMPLEMENTATION BY USING EARNED VALUE ANALYSIS (CASE STUDY: SHRIMP CULTIVATION DEVELOPMENT PROJECT WITH AREA-BASED IN KEBUMEN REGENCY). Vol. 14.
  10. Yulita, Silvia, and Ratih 1. Dody Irnawan. n.d. "Analysis of Final Schedule and Cost Projections with the Earned Value Concept on Construction Projects."